How to Import a Crane from China: Incoterms, Shipping, and Installation
Cross-border purchases of cranes carry plenty of real-world snags. A lot of procurement teams fixate solely on the crane’s mechanical details and skip ahead on logistics planning, paperwork prep, and site setup. These oversights commonly rack up port detention charges, slow project timelines, and create unplanned extra spending.
Multiple export projects demonstrate that even if the equipment meets the agreed-upon technical specifications, a failure by the importer to prepare the necessary documentation, port logistics, and on-site civil engineering can still stall the entire manufacturing project. Therefore, today we’ll discuss the key factors companies should consider when procuring bridge cranes from Chinese manufacturers.

First, Figure Out What You’re Actually Buying
This sounds obvious, but it trips people up. An overhead crane isn’t a single product you pull off a shelf. It’s a system—bridge, hoist, end trucks, controls, runway rails, festoon systems, the works. And Chinese factories build them to order.
That means you need to nail down specs before anything else. Think capacity, span, how high it needs to lift, duty class, voltage, and how you want to control it. Get the voltage wrong, and you’re in for a headache. A crane built for 380V/50Hz won’t play nice with a 480V/60Hz building. Converting it after the fact costs real money.
Weihua and other large manufacturers handle this fine, but only if you give them accurate information upfront. Changing specs after production starts? That’s where timelines fall apart.
Incoterms: Pick One and Stick With It
Here’s the thing about Incoterms—most buyers overthink this.
FOB is what I’d recommend for anyone who’s done this before. Your supplier gets the crane to the port and loads it. After that, it’s your show. You book the freight, you handle insurance, you control the timeline. More work, but you see where every dollar goes.
CIF is easier. The supplier arranges shipping and insurance to your port. First-timers usually go this route because it’s one less thing to manage. Nothing wrong with that. Just know you’re paying a bit extra for the convenience, and you won’t have much say in which vessel your cargo ends up on.
EXW? Skip it unless you’ve got people on the ground in China. You’d be responsible for inland transport, export clearance, everything. Not worth the headache for most buyers.
How Cranes Actually Ship
Nobody sends a crane as one piece. The factory breaks it down—girders here, hoist unit there, electrical panels in crates. A standard 10-ton overhead crane usually fits in two or three 40-foot containers. Bigger cranes need flat racks or breakbulk vessels.
Then add port handling, customs, and trucking to your site. Another week or two, realistically.
The paperwork side is where people get burned. Bill of lading, commercial invoice, packing list, certificate of origin. If your country requires specific certifications, those too. Miss something and your container sits at port while you sort it out. Storage fees aren’t cheap.

Customs and Duties: What to Expect
Duty rates on cranes swing pretty widely depending on where you’re importing.
Here’s a rough way to think about it: a crane quoted at $50,000 FOB won’t land at your door for $50,000. Freight, insurance, duties, inland transport—they add up. You could easily be looking at $70,000 or more by the time it’s all said and done. Keep that in mind when you’re budgeting.
Installation: The Part Everyone Underestimates
This is where projects go sideways.
The crane arrives. Your crew opens the containers. And then someone realizes the runway beams don’t match the drawings, or the power supply isn’t where it needs to be, or nobody ordered the right anchor bolts.
Chinese manufacturers provide foundation drawings and runway specs when you order. Share those with your civil engineer and electrician immediately. Not next month. Now.
Most factories offer installation supervision—a technician comes out to guide your local crew. Costs run $100-200 per day plus travel. Worth every penny if your team hasn’t installed this type of crane before.
For specialized equipment—foundry cranes, process cranes, anything with unusual requirements—consider hiring the manufacturer’s full installation team. It costs more, but you avoid the guesswork.
Testing and Handover
Before the crane lifts anything for real, it needs a load test. Most countries require proof testing at 100-125% of rated capacity with a qualified inspector watching. The manufacturer should provide test certificates, material certs, and wiring diagrams.
Train your operators before you put the crane into service. A crane that’s installed perfectly but operated wrong will fail early, and warranty claims get ugly when misuse is involved.
Frequently Asked Questions
How long does the whole process take?
Production usually runs 30-60 days depending on complexity. Then ocean transit adds another 2-6 weeks on top of that. Customs clearance, inland delivery, installation—it all stacks up. Plan for 2-4 months from order to a working crane.
Which Incoterm should a first-time buyer choose?
CIF. The supplier handles freight and insurance, which removes a lot of moving parts. Once you’ve done a few imports, FOB often saves money.
Do I really need a customs broker?
Unless you import regularly and know the process cold, yes. A broker handles HS classification, duties, and keeps your cargo from sitting at port.
Can the manufacturer install the crane for me?
Most Chinese manufacturers offer installation supervision or full installation. Pricing depends on your location and the crane’s complexity.
What certifications should I ask for?
CE certification for Europe, ISO 9001, and whatever your country requires. Also request material test certificates, load test reports, and electrical schematics.
What if something arrives damaged?
Inspect everything before signing delivery receipts. Take photos. File claims with your insurer right away. Good manufacturers replace damaged parts, but documentation speeds up the process.